NOTICE: Port of Everett's Mukilteo Interim Parking Lot Opening Delayed; Awaiting Permits

Date: Sep 1, 2022

(Lot update as of 9/1/22)

Unfortunately, there was a snag with the permitting interpretation for the property that wasn’t anticipated. We have been told this could delay opening of the lot up to 120 days, but hopefully more like 30-45 days.

We respect the City’s permitting process and will continue to work as fast as we can to get this lot open to the community.